Four detached homes going up on a single landscaped corner in West Cambridge. This page tracks the work as it happens — what is finished, what is underway right now, and what comes next. No renderings standing in for progress. Photographs from the site, updated as each phase closes.

Updated September 2026

A development by

4 Griswold Street from the street, weather-tight with windows set
September 2026 — four detached homes, weather-tight and closing in on delivery.
4Detached homesNo shared walls
9,002SF corner parcelConcord & Griswold
49.4%Open space30% required
34′-6″Building height45′ allowed
Five phases complete · two underway · nine total
Structure closed in · interiors and site work in progress
01
Complete Summer 2025

Site Preparation

Before anything went up, the corner had to be read carefully. The lot at Concord Avenue and Griswold Street is 9,002 square feet, and the plan committed nearly half of it to open space — so the first decisions were about what stays, not what goes. Two mature canopy trees were identified for preservation and protected in place for the duration of construction. The existing structure came down, the site was cleared and surveyed, and erosion control and tree protection fencing went in before a single machine started digging.

  • Parcel9,002 SF corner lot
  • ApprovalsBuilt as-of-right — no zoning relief required
  • PreservedTwo mature canopy trees protected in place
The parcel cleared and graded, with the first floor decks going down at the far edge
The parcel cleared and graded, with the first floor decks going down at the far edge.
02
Complete Fall 2025

Excavation & Foundation

Four separate holes, four separate foundations. Because these are detached houses rather than a single building carved into units, each residence sits on its own footprint with its own footings and foundation walls — and the gaps between them, 13 feet 6 inches and 10 feet 6 inches, had to be held precisely from the ground up. Excavation went deep enough to give every home a full finished garden level rather than a utility basement, which is where the fourth bedroom, full bath, family room and laundry eventually land.

  • FoundationsFour independent structures
  • Separation13′-6″ and 10′-6″ between buildings
  • Below grade730–768 SF of finished space per home
Excavation and grading underway, decks taking shape beyond
Excavation and grading underway, decks taking shape beyond.
Foundation forms and rebar set in mid-winter, ready for the pour
Foundation forms and rebar set in mid-winter, ready for the pour.
Why this phase matters more than it looks. The separation between structures is what makes these single-family homes rather than townhomes. It is set here, in concrete, and it cannot be adjusted later.
03
Complete Winter 2025–26

Framing & Structure

Three stories above grade went up on each of the four foundations, and the shape of the neighborhood-scaled decision became visible for the first time: at 34 feet 6 inches, these homes sit a full ten and a half feet below the 45 feet zoning allows. The floor plates went in at roughly 740 to 780 square feet each on the first and second levels, with a smaller third floor given over entirely to the primary suite — and the roof framing shaped to carry a private terrace off each one.

Inside, the stair is the piece that tells you what kind of house this is. It runs all four levels — garden floor to roof terrace — framed open so that from the bottom tread you can see daylight at the top. Fitting that into a footprint this size is most of the reason the plans went through as many revisions as they did.

  • Height34′-6″ against 45′ allowed
  • StoriesThree above grade plus garden level
  • Third floorFull-floor primary suite, each home
  • Above grade1,949–2,042 SF per residence
Two of the four framed and sheathed, ZIP panels taped and sealed
Two of the four framed and sheathed, ZIP panels taped and sealed.
Two homes framed and sheathed, the third rising behind
Two homes framed and sheathed, the third rising behind.
First-floor deck framing in the January sun
First-floor deck framing in the January sun.
The enclave taking shape
The enclave taking shape — separate structures on separate footprints.
Stair framing and floor joists
Stair framing and floor joists — the garden level open below, third floor above.
Three storeys of stair, framed and walkable
Three storeys of stair, framed and walkable.
04
Complete Winter–Spring 2026

Roof & Weather Envelope

Dried in. Pella windows set, the high-reflectance cool roof and terrace membranes installed, and the full weather barrier closed up so the interiors could begin. The roof specification here is doing double duty — it is a performance decision as much as a material one, carrying a solar reflectance index of 98 and contributing to a Cambridge Cool Factor score of 3.24 against a passing threshold of 1.0.

  • WindowsPella throughout
  • RoofHigh-SRI cool roof — SRI 98 initial, 87 aged
  • Cool Factor3.24 score · 1.0 required
From Griswold Street
From Griswold Street — weather-tight, windows set, siding still ahead.
A Pella unit staged against the wall, waiting to go into its opening
A Pella unit staged against the wall, waiting to go into its opening.
Terrace deck and cool roof membrane down, parapet sealed
Terrace deck and cool roof membrane down, parapet sealed.
Looking across to the next home
Looking across to the next home — all four weather-tight. Siding still to come.
Mature canopy from the third floor
Mature canopy from the third floor — the reason two trees were protected on day one.
05
Complete Spring 2026

Rough-In, Insulation & Drywall

The systems that make these homes all-electric went in behind the walls: air-source heat pumps for both heating and cooling, energy recovery ventilation bringing filtered fresh air into every room, and electrical serving a building with no gas line to it at all. Cambridge’s fossil-fuel-free declaration applies here, and the homes are built to the Massachusetts Specialized Stretch Code. Once inspections cleared, insulation and drywall closed the walls for good — followed by door casings and trim.

It is worth saying plainly what is now invisible. There is no gas line to this property. Heating, cooling, hot water and cooking all run on electricity, and the ventilation system brings filtered outside air into every room rather than relying on an open window. Those decisions are permanent, they were made before the walls closed, and they are the difference between a house that meets code and one built to the Commonwealth’s Specialized Stretch Code.

  • HeatingAir-source heat pump · 10 HSPF2
  • CoolingAir-source heat pump · 20 SEER2
  • VentilationERV fresh-air system
  • CodeMA Specialized Stretch Code, HERS-rated
Afternoon light through the slider and clerestory, walls finished
Afternoon light through the slider and clerestory, walls finished.
Clerestory windows above the slider, drywall finished and ready for floors
Clerestory windows above the slider, drywall finished and ready for floors.
Door casings and trim set through the hall
Door casings and trim set through the hall.
Doors hung and casings set along the second-floor hall
Doors hung and casings set along the second-floor hall.
Light through a full-height window, walls closed up
Light through a full-height window, walls closed up.
06
Underway now Summer 2026

Interior Finishes

This is where the homes stop being construction and start being houses. Flooring is going down — wide-plank Woodland Reserve white oak in a natural finish, already laid through the upper floors — and cabinetry is being set — the kitchens built around Calacatta Claudia stone and panel-ready Thermador appliances, the wet bar that appears in every residence, and the bath program that shifts deliberately as you move through the house: brushed gold in the third-floor primary suite, bronze on the second floor, matte black at the garden level. Large-format matte porcelain, 60-inch alcove soaking tubs, and millwork being fitted room by room.

Cabinetry arrives crated and labelled by room, and every run is checked against an Elleganza shop drawing held up in the space before anything is fixed in place. It is an unglamorous step almost no buyer ever sees, and it is the one that decides whether a kitchen reads as built for the room or dropped into it.

  • KitchenThermador induction · Calacatta Claudia stone
  • MetalsBrushed gold → bronze → matte black by floor
  • Every homeWet bar, laundry room with undermount sink
  • CurrentlyFlooring installed above; cabinetry and appliances staged
The kitchen taking shape
The kitchen taking shape — island cabinetry staged, Thermador range in position, hood still boxed.
Island and perimeter cabinetry wrapped and set, opening to the terrace door
Island and perimeter cabinetry wrapped and set, opening to the terrace door.
White oak down and running toward the light
White oak down and running toward the light.
Flooring meeting the stair landing
Flooring meeting the stair landing.
Woodland Reserve engineered white oak, natural finish
Woodland Reserve engineered white oak, natural finish.
Flooring staged on Ramboard, acclimating before installation
Flooring staged on Ramboard, acclimating before installation.
Woodland Reserve engineered white oak, still boxed
Woodland Reserve engineered white oak, still boxed.
Elleganza cabinetry crated and staged under a skylight, waiting its turn
Elleganza cabinetry crated and staged under a skylight, waiting its turn.
Upper cabinets in place, trim stock stacked and ready
Upper cabinets in place, trim stock stacked and ready.
Bath vanity cabinetry set, plumbing roughed, waiting on stone
Bath vanity cabinetry set, plumbing roughed, waiting on stone.
Elleganza shop drawing checked against the room before anything is fixed
Elleganza shop drawing checked against the room before anything is fixed.
The bath elevation
The bath elevation — vanity, mirror and the patterned tile behind it.
Internal cabinet drawing for Bath 02, checked on site before install
Internal cabinet drawing for Bath 02, checked on site before install.
Stair treads still open
Stair treads still open — among the last interior items.
Thermador range delivered and staged, waiting on cabinetry and countertops
Thermador range delivered and staged, waiting on cabinetry and countertops.
Stone countertop template or install
Calacatta Claudia slabs — a close crop of the veining sells this.
Bath tile installation
Large-format porcelain going up in a bath.
07
Underway now Summer 2026

Grading, Utilities & Landscape

Outside, final grading and the last utility work are running in parallel with the interiors. This is the phase that delivers the thing the site plan has been promising since the beginning: 4,449 square feet of open space on a lot where zoning asked for less than two-thirds of that, and roughly a third of the parcel left permeable at grade. Sixteen trees new and transplanted, joining the two that were protected on day one. Techo-bloc patio pavers, reclaimed boulders and river stone, and six-foot horizontal board fencing defining each home’s own garden.

  • Open space4,449 SF — 49.4% against 30% required
  • Permeable32.3% of the lot at grade
  • Planting16 new and transplanted trees
  • ParkingFour off-street spaces, EV-ready · bike parking
Excavator working the front yard as site work gets underway
Excavator working the front yard as site work gets underway.
Backfill and grading around the foundation, silt fence still in place
Backfill and grading around the foundation, silt fence still in place.
Water and sewer service run in from the street
Water and sewer service run in from the street.
Aerial view of the site during landscape work
Priority drone shot. Overhead frame showing how much of the parcel is landscape rather than building.
Watch this space. Planting is the phase that changes the site fastest. The next set of photographs here will look almost nothing like these.
08
Still to come Fall 2026

Fixtures, Appliances & Final Trim

The last layer. Appliances set and connected — the 36-inch Thermador Professional Induction ProRange, the Masterpiece insert hood, panel-ready refrigeration and dishwashing, the microwave drawer. Plumbing fixtures hung against their floors: the wall-mount pot filler and 32-inch workstation sink in the kitchen, the ceiling-mounted solid brass faucet in the powder room. Paint, final trim, hardware, and the roof terraces finished out.

  • RangeThermador 36″ Professional Induction ProRange
  • Refrigeration36″ Freedom French door, panel-ready
  • SinkRuvati 32″ workstation ledge undermount
  • TerracesPrivate roof terrace finished per home
Appliance installation
Appliances going in. Shoot when the Thermador range is set.
Finished kitchen
First fully finished kitchen — this becomes your hero image everywhere.
Completed roof terrace
Roof terrace at golden hour, looking out over the neighborhood.
09
Still to come Late 2026

Commissioning & Delivery

Every system tested and balanced, the HERS rating issued, final inspections cleared and the certificate of occupancy in hand. Then the part that matters: keys. Four homes, four sets, four households on one corner in West Cambridge.

  • VerificationIndependent HERS rating & blower door testing
  • CommissioningHeat pump and ERV systems balanced
  • FinalCertificate of occupancy & walkthrough
The completed Griswold Collective
The finished project. Until this exists, a rendering can hold the slot — label it as one.

Get the build updates

A short note each time a phase closes — new photographs, what changed on site, and what is coming next. Sent only when there is something to show.

Request updates 4 Griswold Street · Cambridge, MA 02138 · 617 963 6128

Project Team

Developed by
Built by
Marketed & sold by EVO Real Estate Group
4 Griswold Street · Cambridge, MA 02138 617 963 6128 thegriswoldcollective.com